top of page

Project Gallery

Major Amazon Parking Facility

Date: September 2026

Project: Large-scale asphalt surfacing

The delivery of this brand-new parking facility for Amazon required careful coordination, effective project management and the expertise of specialist contractors working together to meet a demanding programme.


Our client, as the main contractor, led the overall project delivery, coordinating the various elements of the development to ensure the facility was completed to the required specification and within the agreed timeframe. Derek Lewis Ltd was appointed as the surfacing subcontractor, responsible for delivering the extensive asphalt works across the site.


12,500 tonnes of asphalt laid in 12 weeks


Working closely within the main contractor's programme, Derek Lewis Ltd laid approximately 

 12,500 tonnes of asphalt to form the new parking facility and its associated Section 278 (S278) access roads.


With significant areas to surface and ambitious production targets to achieve, the works demanded efficient planning, reliable material supply and close coordination with wider site operations. Through this collaborative approach, the surfacing works were completed within the 12-week timeframe set by our client.


Specialist materials and precision level control

Holcim's SuperDrainAsphalt was used across all three asphalt layers within the parking bays, providing a specialist surfacing solution designed to support drainage requirements.


Accuracy across the extensive parking area was achieved using a dual-grade laser system working in conjunction with receivers fitted to the paving equipment. This technology provided precise level references across two axes, helping control material depth during laying and achieve the specified levels and falls.


The use of specialist asphalt materials and laser-guided paving formed an important part of delivering the surfacing element to the required standard.


High production across every layer

The scale of the development called for substantial daily output. Derek Lewis Ltd's surfacing operations achieved production rates of:


  • Approx.      1,000 tonnes of road base per shift

  • Approx.       650 tonnes of binder course per      shift

  • Approx.       500 tonnes of wearing course      per shift


Achieving these rates required effective coordination between material deliveries, our paving team and the wider construction programme. This work formed part of the combined effort needed to keep the project progressing efficiently.


A successful project delivered through collaboration

Completing a development of this scale within 12 weeks was a significant undertaking, requiring strong project coordination and the effective integration of multiple workstreams.


Through our client's overall management and delivery of the project, supported by Derek Lewis Ltd's high-volume surfacing operations and precision paving techniques, the new Amazon parking facility was completed within the required timeframe.


The project demonstrates the value of experienced contractors working together, with our client leading the wider development and Derek Lewis Ltd delivering a substantial and technically demanding element of the works.

Contact Us

At Derek Lewis we take great pride in providing our customers with the high-quality services they deserve. Our team is available to answer any questions you may have and to help you with your project. We look forward to hearing from you!

By entering your information and clicking on submit you are agreeing to our privacy terms & conditions!

Thank you for your enquiry.

Derek Lewis Ltd head office in Doncaster

Balby Carr Bank, Doncaster, DN4 8DE

01302 875078

Derek Lewis Ltd accreditations

Trusted and Accredited by UK Leading Authorities

©2024 DerekLewis Ltd. All Rights Reserved

bottom of page