West Moor Link exceptional maintenance scheme

West Moor Link exceptional maintenance scheme

Posted: October 19, 2009 
Filed under: Derek-Lewis

Description

Working in conjunction with DMBC’s Highways Department we completed the £2.3 million A630 West Moor Link Exceptional Maintenance Scheme, a project of some scale.

A six phase project running over several periodical closures, our role was to plane out the existing kerb line and bituminous material, retread, grade and compact the exposed cementitious sub base, lay type 1 stone to form new build up levels and lay road base and binder course.

Further closures in the subsequent weeks when the carriageway was trafficked allowed masons to install kerbs, channels and set iron works to the desired levels. With civils works complete we returned to surface all footways, lay the binder and SMA surface courses.

The project was completed on time through the successful collaboration of ourselves, DMBC and other trusted sub contractors who all employed professionalism, dedication and hard work throughout.

Recent Photos

Mini Construction Team! New addition to the Derek Lewis Fleet Doncaster Castle Knights Under 17s South African Rugby Tour New Shiny Offices! Welcome to Doncaster! Sidings Roundabout sponsored by Derek Lewis New Team Member & Service Eco friendly BMW L100 SUK – Derek Lewis Road Sweep Fit, healthy and regular!